FAR 45.105 establishes the requirements for Government oversight of a contractor’s property management system and prescribes the administrative actions and penalties triggered when a system fails to meet contractual standards.
Key Rules
- System Analysis: The administrative contracting agency is required to periodically analyze the contractor’s property policies, procedures, and practices based on current conditions and agency-specific procedures.
- Notification and Correction: When deficiencies are identified, the Property Administrator (PA) must provide written notification, requesting a formal corrective action plan and a completion schedule from the contractor.
- Escalation to Contracting Officer: If the contractor fails to follow the corrective action schedule, the Contracting Officer (CO) must warn the contractor that non-compliance may lead to severe remedies.
- Remedies for Non-compliance: The Government may revoke its "assumption of risk" for loss of Government property or exercise other contractual rights and remedies.
- Liability Determinations: The PA determines whether the Government assumes the risk for lost property (granting "relief of stewardship") or whether the CO should hold the contractor financially liable for the loss.