← All Free ToolsGo back to previous tools page
Explore More Tools →
section49.607

Delinquency notices

Overview

This section prescribes the standardized formats and procedural requirements for issuing "Cure Notices" and "Show Cause Notices" to contractors as a prerequisite for a Termination for Default under FAR 49.402-3.

Key Rules

  • Proof of Delivery: All delinquency notices must be sent using a method that provides proof of delivery.
  • Cure Notice Requirements:
    • Issued when a contractor’s failure endangers contract performance before the delivery date.
    • Can only be used if there are 10 or more days remaining in the contract delivery schedule (or an extension thereof) to allow for a realistic cure period.
  • Show Cause Notice Requirements:
    • Issued if the delivery date has passed or if the remaining time in the schedule is less than the 10-day minimum required for a Cure Notice.
    • Provides the contractor 10 days to present written evidence that the failure arose from causes beyond their control and without their fault or negligence.
  • Non-Waiver of Rights: The government's acceptance of delinquent goods or any assistance provided to the contractor does not constitute a waiver of the government's legal rights or a condonation of the delinquency.

Practical Implications

  • Contracting Officers must strictly monitor delivery schedules; issuing a Cure Notice with insufficient time remaining (less than 10 days) can be a procedural error that complicates a termination action.
  • These notices serve as a critical due-process mechanism, providing a "paper trail" that protects the government’s interests if a termination is later challenged in the Board of Contract Appeals or Court of Federal Claims.

Need help?

Get FAR guidance, audit prep support, and proposal insights from the AudCor team.

Talk to an expert