← All Free ToolsGo back to previous tools page
Explore More Tools →
subpart9.3

Subpart 9.3 - First Article Testing and Approval

FAR Subpart 9.3 outlines the policies and procedures for First Article Testing (FAT) and Approval, a quality assurance mechanism used to ensure a contractor can

Analysis of FAR Subpart 9.3 - First Article Testing and Approval

Overview

FAR Subpart 9.3 outlines the policies and procedures for First Article Testing (FAT) and Approval, a quality assurance mechanism used to ensure a contractor can manufacture products that strictly conform to contract requirements before full-scale production begins. This subpart balances the Government's need for risk mitigation against the potential impacts on cost, delivery schedules, and contractor financial risk.

Key Rules

  • Purpose of FAT: The primary goal is to verify that a contractor can furnish a product that meets all contract specifications for acceptance.
  • When to Require FAT: It is typically used for new products, new contractors, significant changes in manufacturing processes, or after a long hiatus in production.
  • Standard Exceptions: FAT is generally not required for Research & Development (R&D) contracts, products sold in the commercial market, or products already on a Qualified Products List (QPL).
  • Risk Allocation: Production or material acquisition performed before FAT approval is at the sole risk of the contractor unless the Contracting Officer specifically authorizes it to meet a demanding delivery schedule.
  • Waiver Eligibility: The Government may waive FAT requirements if the contractor has previously delivered identical or similar supplies that were accepted by the Government.
  • Evaluation Factors: If the Government performs the testing, the estimated testing costs must be included as a factor in evaluating offers. Additionally, the price for first articles must not be "materially unbalanced" compared to production quantities.
  • Formal Changes: Any changes to designs or specifications identified during the FAT process must be formalized via the "Changes" clause, not merely through the notification of approval or disapproval.

Responsibilities

  • Contracting Officer (CO):
    • Determines if FAT is necessary by considering cost, time, and risk.
    • Decides whether the Contractor or the Government will conduct the testing.
    • Authorizes (if necessary) the acquisition of materials prior to approval.
    • Formally notifies the contractor in writing of approval, conditional approval, or disapproval.
  • Contractor:
    • Conducts testing (if specified) and submits detailed test data/reports to the Government.
    • Bears the financial risk of production prior to approval unless otherwise authorized.
    • Produces the first article and production quantities at the same facility (if Alternate I of the clause is used).
  • Government Laboratory/Testing Activity:
    • Conducts the testing (if specified) or evaluates the contractor’s test report.
    • Advises the Contracting Officer on whether to approve or disapprove the article.
  • Contract Administration Office:
    • Provides advance notification to the testing laboratory regarding shipments.
    • Monitors the timeline for testing completion.

Practical Implications

In real-world government contracting, First Article Testing is a significant "gate" that can impact a project's critical path. For contractors, FAT represents a period of high financial exposure; if they begin production early to meet a tight deadline and the first article fails, the Government is not liable for the wasted costs. For the Government, FAT is an essential safeguard for complex or "exacting" items where a manufacturing error could lead to a fleet-wide defect.

Pro-Tip for Contractors: Always look for the waiver provision in solicitations (FAR 9.306(c)). If you have successfully delivered the same item under a previous contract, providing those contract numbers can save months of testing time and significant costs, often making your proposal more competitive on both price and schedule.

Need help?

Get FAR guidance, audit prep support, and proposal insights from the AudCor team.

Talk to an expert